EP No. EP-458/2013/C
Tseung Kwan O – Lam Tin Tunnel Design and Construction

Environmental Permit Submissions

Silt Curtain Deployment Plan

NE/2015/01

May 2017

Silt Curtain Deployment Plan

NE/2015/02

August 2019

September 2019


January 2020

Silt Curtain Deployment Plan

NE/2017/01

 June 2019


January 2020

Coral Translocation Plan

February 2016

Management Organization of Main Construction Companies

NE/2015/01

September 2016

Management Organization of Main Construction Companies

NE/2015/02

September 2016

Management Organization of Main Construction Companies

NE/2015/02

February 2017

Management Organization of Main Construction Companies

NE/2015/02

February 2018

Management Organization of Main Construction Companies

NE/2017/02

February 2019

Management Organization of Main Construction Companies

NE/2017/06

October 2020

Construction Programme

NE/2015/01

September 2016

Construction Programme

NE/2015/02

September 2016

Construction Programme

NE/2015/03

February 2017

Construction Programme

NE/2017/01

February 2018

Construction Programme

NE/2017/06

October 2020

Waste Management Plan

NE/2015/01

July 2017

Waste Management Plan

NE/2015/02

October 2016

Waste Management Plan

NE/2015/03

May 2017

Waste Management Plan

NE/2017/01

March 2018

Waste Management Plan

NE/2017/02

March 2018

Waste Management Plan

NE/2017/06

December 2020

Noise Mitigation Plan

NE/2015/01

September 2016

July 2022

August 2022

Noise Mitigation Plan

NE/2015/02

November 2017

July 2022

Noise Mitigation Plan

NE/2015/03

September 2017

Noise Mitigation Plan

NE/2017/01

March 2018

April 2019

Noise Mitigation Plan

NE/2017/02

December 2018

Noise Mitigation Plan

NE/2017/06

August 2021

Built Heritage Mitigation Plan

NE/2017/02

July 2018

Water Gate System and Temporary Steel Cofferdam Design Report

NE/2015/02

July 2017

Sediment Management Plan

NE/2015/02

November 2016

Landscape Mitigation Plan

May 2019